Distribution network upgrade
Increasing demand on the electricity network due to new industrial/commercial facilities being built in the area was identified as major network risk likely to result in power outages unless resolved. TSA were engaged by CitiPower to implement a solution that would resolve this immediate issue and future proof the network for additional capacity requirements over the coming years.
Complex stakeholder engagement:
- Metro trains interface management due the abutting rail line
Dyson (bus) due to bus stop relocation and customer disruption management - Merri-bek (Moreland) City Council for road closure permit
Urban Athletic 24/7 Gym access management - Notifications to local residents, commuters and businesses
- Utility asset owner liaison and design solution approval to ensure all clearances and solution design met all their standards and requirements.

Featured Case Studies
Civil and structural buildings, electricity and communications asset construction.
Since 2019, we have delivered six projects [⁓$17M] NEXTDC M2 – Stage 1,5,6,8 and Microsoft DC – MEL04&05
Complexities
- Navigating complex requirements and standards in relation to data centre early works and construction.
- Interfacing with diverse contractors across the data centre site to ensure safe, timely and seamless delivery of our required scope of works.
- Critical pathway procurement items and activities related to our works and the broader works.
Civil and structural buildings, electricity and communications asset construction.
Since 2019, we have delivered six projects [⁓$17M] NEXTDC M2 – Stage 1,5,6,8 and Microsoft DC – MEL04&05
Complexities
- Navigating complex requirements and standards in relation to data centre early works and construction.
- Interfacing with diverse contractors across the data centre site to ensure safe, timely and seamless delivery of our required scope of works.
- Critical pathway procurement items and activities related to our works and the broader works.
Civil and structural buildings, electricity and communications asset construction.
Since 2019, we have delivered six projects [⁓$17M] NEXTDC M2 – Stage 1,5,6,8 and Microsoft DC – MEL04&05
Complexities
- Navigating complex requirements and standards in relation to data centre early works and construction.
- Interfacing with diverse contractors across the data centre site to ensure safe, timely and seamless delivery of our required scope of works.
- Critical pathway procurement items and activities related to our works and the broader works.